Weekly Users' Meeting Minutes -- October 14, 2009
Schedule
X-ray: Template time cancelled for Tuesday 10/20/09, 2000 - 2400 hrs. Time is returned to normal operations.
VUV: Timing run cancelled for Monday 10/19/09, 1800 - 2400 hrs. Time is returned to normal operations.
**The official weekly x-ray ring schedule is posted on NSLS TV Channel 11, which is also available
on the schedules page by click on Short Range Schedules.
**The official weekly VUV ring schedule is posted on NSLS TV Channel 5, which is also available
on the schedules page by click on Short Range Schedules.
Machine Status
The x-ray ring switched over to 30 bunch mode this past Saturday morning, 10/10/09. No one reported any problems with the new bunch mode.
The cooling water test last Thursday and Friday went smoothly (20 minutes to switch to the on-site system and about 40 minutes to switch back). A longer test will be planned before the shutdown.
Proposed Schedule for January - April 2010
The proposed schedule for Jan - April 2010 was shown and is included in the attached file. Please send Emil (zitvogel@bnl.gov) your comments as soon as possible. Major jobs that are planned for the December Shutdown are: 1) The X7 mask will be worked on and may need to be replaced. If replacement is necessary, it will involve a complicated bakeout, since it includes the injection area. 2) Water Tower maintenance- The dunnage (support for the water tower), as well as the water tower itself may need to be replaced. This effort depends on the on-site water being switched in, and being relied upon until potentially the end of February. 3) The X17 hutch and transport section will be reworked for X17A and then the radiation levels will be checked after the shutdown.
NSLS II Construction – Soil Compacting
The large compactor may be in operation in the NW corner of the site 10/19/09 - 10/23/09 and 10/26/09 - 10/30/09.
Elevator Update - Bob Kiss
The work on the lobby elevator will start very soon (maybe Friday) and could take as many as 4-6 weeks, but may be completed in as little as 3 weeks.