Weekly Users' Meeting Minutes -- April 29, 2009
Schedule
X-ray: No special requests.
VUV: U. of Florida group is planning to come for timing runs during July. Their proposed timing schedule is:
July 10: 1800 – 0230 Timing 7 bunch detuned [1800 – 2400 Scheduled Timing] July 11: 1800 – 0230 Timing 7 bunch detuned July 12: 1800 – 0230 Timing 7 bunch detuned July 13: 1800 – 0230 Timing 7 bunch detuned [1800 – 2400 Scheduled Timing] July 17: 1800 – 0230 Timing 7 bunch compressed [1800 – 2400 Studies] July 18: 1800 – 0230 Timing 7 bunch detuned July 19: 1800 – 0230 Timing 7 bunch detuned July 20: 1800 – 0230 Timing 7 bunch detuned July 21: 1200 – 2400 Timing 7 bunch compressed [0800 – 2400 Studies] July 22: 1200 – 2400 Timing 7 bunch compressed [0000 – 2400 Studies]
**The official weekly x-ray ring schedule is posted on NSLS TV Channel 11, which is also available
on the schedules page by click on Short Range Schedules.
**The official weekly VUV ring schedule is posted on NSLS TV Channel 5, which is also available
on the schedules page by click on Short Range Schedules.
Machine Status
Both rings are running well.
May Shutdown
Experimental water and compressed air will be turned off on Mon 5/4/09 at 1000 hrs. Water and air systems will be turned back on 5/18/09.
Electrical Substations 1, 2, 3 and 4 will be shut down on Saturday 5/9/09.
Operations Coordinators will be on daytime staffing only during shutdown starting 5/4/09. 24 hr staffing resumes 5/18/09.
X-ray Shutdown begins 0600 hrs, Mon 5/4/09
VUV Shutdown begins 0600 hrs, Mon 5/4/09
Exp. Water & compressed air off 1000 hrs, Mon 5/4/09
Water & Air Systems on - Full Op 0800 hrs, Mon 5/18/09
LN2 and GN2 off 0800 Mon 5/11/09 - 1700 Thurs 5/14/09)
Booster Commissioning 0800 hrs, Mon 5/18/09 - Tues 5/26/09
VUV Commissioning Mon 5/18/09 - Tues 5/26/09
X-Ray Commissioning Tues 5/26/09 - Fri 6/5/09
VUV Full Operations Tues 5/26/09
X-ray Full Operations Fri 6/5/09
Automatic LN2 filler will be installed over the shutdown.
Plug doors to be opened: X7-8, X11-12, X17-18, X25-26, X27-28 and X29-30.