Weekly Users' Meeting Minutes -- June 17, 2009
Schedule
X-ray: No special requests.
VUV: Timing run cancelled for Monday 6/22/09, 1800 - 2400 hrs Time is returned to normal operations.
U. of Florida group is planning to come for timing runs during July. Their proposed timing schedule is:
July 10: 1800 0230 Timing 7 bunch detuned [1800 2400 Scheduled Timing] July 11: 1800 0230 Timing 7 bunch detuned July 12: 1800 0230 Timing 7 bunch detuned July 13: 1800 0230 Timing 7 bunch detuned [1800 2400 Scheduled Timing] July 17: 1800 0230 Timing 7 bunch compressed [1800 2400 Studies] July 18: 1800 0230 Timing 7 bunch detuned July 19: 1800 0230 Timing 7 bunch detuned July 20: 1800 0230 Timing 7 bunch detuned July 21: 1200 2400 Timing 7 bunch compressed [0800 2400 Studies] July 22: 1200 2400 Timing 7 bunch compressed [0000 2400 Studies]
**The official weekly x-ray ring schedule is posted on NSLS TV Channel 11, which is also available
on the schedules page by click on Short Range Schedules.
**The official weekly VUV ring schedule is posted on NSLS TV Channel 5, which is also available
on the schedules page by click on Short Range Schedules.
Machine Status
Network problems starting early Saturday morning 6/13/09, x-ray & VUV refills postponed. Network restored before noon.
VUV noise reported Sunday 6/14/09 by U2. Investigation of longitudinal feedback system done yesterday 6/16/09 during Studies.
Proposed Schedule for September-December 2009
Emil Zitvogel showed a draft of the September-December 2009 schedule (see attached file)
TV monitor
Ch 14 now displays a real-time monitor of the vacuum pressure inside the x-ray and VUV rings.
July 4 Break
There will no overhead lights on the NSLS floor (hutch and hall lights will be available) during the July 4th holiday: Wednesday, 2000 hrs, 7/1/09 - Monday morning, 7/6/09.
Water systems will be turned off starting Wednesday, 7/1/09, at approximately 2100 hrs. The water systems wont come on until Tuesday, 7/7/09, at approximately 0800 hrs.
Automatic LN2 fill system will be down 6/29/09 - 7/6/09 in order for control unit to be sent back to the company for the repair of a defective solenoid valve. There will be the capability of filling dewars manually.