Archive: 2009 | 08 | 07 | 06 | 05

Weekly Users' Meeting Minutes -- September 2, 2009


Schedule

X-ray: No special requests.

VUV: Timing runs cancelled for Friday 9/4/09 and Monday 9/7/09,
1800 - 2400 hrs. Time is returned to normal operations.

**The official weekly x-ray ring schedule is posted on NSLS TV Channel 11, which is also available on the schedules page by click on Short Range Schedules.

**The official weekly VUV ring schedule is posted on NSLS TV Channel 5, which is also available on the schedules page by click on Short Range Schedules.



Machine Status

Both rings are running well.

X-ray beam expected back on by 8 tonight.

X9's beam position was off. Studies carried out by the accelerator group
found a better orbit position for X9. Observation studies of this orbit
bump will be scheduled at a future date.

There was a problem with one of the power supplies for the VUV. Technicians are
working on it and the problem is expected to be resolved before 1 PM today.



Cybersecurity Audit

There will be a cyber-security review/audit this week. Users are advised to protect
their computing facilities by having password-enabled screen saver and lock their
offices when not in.


NSLS II Construction – Soil Compacting

There are no large compactor activities scheduled in the NW corner of the site until
9/14. Between 9/14 and 9/18, the large compactor will be in operation intermittently
in the NW corner of the site.


Lab Holiday

Please note that Monday 9/7/09, Labor Day, is a lab holiday and
most NSLS staff will be unavailable. The Control Room and OPCOs
will be on duty.



 

Subscribe to the email list for X-Ray and VUV minutes and schedules